Things remain similar here. Cases are rising. School seems uncertain. Work is busy. House is moving along slowly. Wedding is approaching. 






The garage doors will be white, as well.


6 comments:

ET said...

The front door will be black.

Tanya said...

How much longer on the house?

ET said...

Months

Still have to: stucco, garage doors, finish floor tile, cabinets, shower tile, stair rails, carpet, lights, closets, counters, driveway, etc.

The outside is more done than the inside.

ET said...

Maybe October at earliest.

Galen Tromble said...

That seems like 2 weeks work at least.

ET said...

Ha ha. Well, Covid doesn't help because they only have one sub at a time.